Dig Report
We
had a good training session at the Committee Rooms (not the Glebe!)
and had the opportunity of welcoming Dave, Ellie and Rob. Hopefully to be
joined by some more over the coming weeks. I think we all learnt
something and refreshed some of the grey matter.
Generally
the site faired quite well over the winter although we now know the
plastic sheet is not UV proof! Whilst windy it was bright so generally a
pleasant day to work. After tucking up QA: QB & QD we cleared the
weeds from the "legal quadrant" QC. After discussions with
Aileen we have decided to excavate 2x 1 metre wide
trenches down to the original soil level. This should ensure we can
complete a good survey of the mound to enable us to be able to write our report
within the next year. The excavation will be by mattock and trowel so
hopefully will be quicker and we may be able to surprise ourselves and complete
more than the trenches.
We
hope to be on site every Saturday from now to the autumn/winter from 12.30
onwards. In addition, Liz is going to try some evening digs like last
year. Aileen is also going to see if the
Dig Report
Saturday
was a great day for digging, nice sunshine and gentle breeze so the temperature
was ideal. The soil is still moist under the top layer so again was good
to excavate.
The
numbers progressively increased during the afternoon so we ended up as the
"Magnificent Seven", (Gill, Alex, Kim, Gae
and Clive plus Irene and self). Welcome to Gae
and to her first dig. At the end she commented she was still not sure
what we were doing - well you are now in good company as after 3 years
most of us still feel the same way!!!!!!!!!!!!!
From
the pictures you will see we have taken the north/south trench in quadrant C
down to the first soil change and are well on the way in getting the east/west
trench down to the same layer. It will be interesting to get the dumpy
level on it but it appears to my drunken eyes as though this soil change drops
away from the test pits we started to excavate at the end of last year.
If so, it does tend to reconfirm our estimate of where we think the centre is.
We
found quite a large piece of worked flint and a very round (sling-shot???)
stone.
We
look forward to seeing you on site this Saturday for as long or short as you
can make it. We look forward to seeing Aileen (with hiking boots and
rucksack!). At this stage the plan is to continue to take down the
east/west trench to the same soil change as the north/south trench and hopefully
start taking them both down to the next context change. If you are not up
to digging you will still be very welcome as there are other jobs that need to
be done like recording the location of last week's finds and hopefully all this
week's haul, draw the plan for quadrant C and maybe start the section drawings.
Dig Report
Last
week we again had good weather although another week without rain made the
surface dry and hard. Thank goodness for mattocks! Another good
turnout with a Super 6 which increased to another Magnificent 7, when
Aileen popped in to make sure we knew what we should be doing over the next few
weeks. All our best wishes for the stroll across
In
addition to Gill, Jane (apologies I missed you from the photo shoots) Irene and
myself, we welcomed Peter and Colin. Both are experienced metal detectors
but have not had the chance to get down and dirty before. They have
threatened to return so must have enjoyed the experience!
We
continued to dig out the trenches. At the end of a days digging it
appears as though more has been achieved than when we evenly take the whole of
a quadrant down! We found some nice flints, especially a fine one by
Jane. I attach a quick picture as well as the other ones I took on the
day.
Dig Report
he
sun was still shining and the small amount of rain there had been the days
before was as good as nothing. This did not deter the energetic
eight. Yes, 8 of us - Gill, Colin, Elie, Clive,
Dave and Alex as well as Irene and myself.
We
continued excavating the trenches and then had a rest from being on our knees
by recording the locations of the previous weeks finds. This was good
revision for Clive and Elie and was something totally
new for Colin. Don't worry Colin, I won't test you next week, but
probably will the week after. Only joking! I am sorry to say that
the finds this week were very thin on the ground and amounted to a small piece
of burnt wood found by Clive. Probably from the match he lit his pipe
with! Again only joking as Clive was not smoking only the speed of
his trowel-work. However we did make good progress in shifting quite a
lot of soil.
Dig Report
The
famous (or should it be infamous) five were on duty - Peter whose body has just
recovered from his first dig, Gill who is giving Irene and me a run for the
most attendances, Jane with Freya our new secret
detection weapon plus Irene and self.
It started
a bit on the cool side but by the end it was a glorious sunny day. We
continued reducing the trenches and small finds were again on the thin
side. Only one possible small pointed flint. Even if it is nothing,
it was good training for Peter on recording finds!
In
the area where Gill has been digging the soil seems to have different soil
patches and she discovered 2 very soft mini-trenches about 18cm deep running in
a N -S direction. Initially we thought they were the normal
"mole" plough damage, but looking at the section there did not appear
to be any slump where soil has fallen in from higher soil levels and the sides
seemed a lot straighter with squarer rather than the expected round corners.
We are probably fooling ourselves and it is the plough but another opinion will
be appreciated. Later Jane found the beginning of another similar
mini-trench. They all seem to be about 1.4 m apart. I hope the
photos give an indication of them and in Jane's area you can see where the
new mini-trench continues but still needs to be excavated and a mole plough
mark which is different to Gill's mini-trenches.
We
also cleaned the initial test pit and have taken down the N - S trench to
nearly the same level. We sprayed the main areas we were working on so
hopefully the soil changes are clearer although the one of the original pit I
have also enhanced which whilst it does not show the true colours
does make it easier to identify the differences. The soil change we
found in the centre seems to be running into the NS trench? What are your
views?
We
also did some quick dumpy measures to see how evenly we are excavating the
trenches. I have put these onto the attached word document. You
will see we also took the height of the outside of Quadrant A and the bottoms
of the 2 mini-trenches Gill found are only 5-6 cm above what we believe is the
pre mound original soil level.
Dig Report
The
4 Musketeers were in action on Saturday. New members Elie
and Peter kept Irene and myself company on a day when the conditions for
digging were great but initially a bit miserable weather-wise. We
started with a tidy-up of QC. With the rain and warmer weather the
weeds had grown! With the expectation the Ely Standard photographer
will join us this Saturday and Taleyna's first visit
since the global positioning survey, I thought we should look
Professional. Note that is Professional with a capital P!
We
decided to leave the centre area of the trenches alone, even though it is
likely the mini trenches are mole ploughing but they
do seem to be deeper than we have found before. Alex has e-mailed Richard
to see if they have any idea how deep they could have mole ploughed Mr Lee's land. The trenches are now getting quite
deep although there is probably still about 20 cm before it is down to the base
level.
The
rest of the team had a find apiece, sorry for letting the side down. 2
flints and a piece of charcoal which "has not been touched by human
hand" that is large enough to have a carbon dating test, if we decide we
want to.
As
mentioned above Liz hopes the Ely Standard photographer will visit the
site, maybe with the reporter to do a follow-up article after the one published
at Christmas last year. I think it will be great if we could have as many
as possible on site even if you can't stay long and or can't dig. Just
come to swell the numbers and see how we have progressed. Pictures only
show part of the story!
Dig Report
As
we were having the photographer from the Ely Standard visiting us, we did a
clear of the trenches and sections. There are a series of photos that
hopefully show the various context changes. By the time Frazer the
photographer arrived we had continued digging and "spoiling" the
cleaned surfaces. But that is what you have to do to make progress!
The
we, was Jane, Peter, Irene and self and we greatly appreciated the support and
all the hard work that Taleyna gave us. I trust
Taleyna the muscles were not too sore after
all your work.
We
continued to take the trenches down and near the area where we believe the
centre is, found a large band of gravel that appears to be over the grey soil
layer. Jane gave us a beautiful theory that it could be from when the
area started having floods at the end of the bronze age/early iron age which
could have washed the gravel from the rivers covering the mound. This was
then spoilt by Jane confessing that archaeology is great as you can make up
your theories and Taleyna stating how many debate if
it is a science or an art! At the end of a good days digging where the
weather was kind, we all agreed is was just "hard work"!
Dig Report
The
rain before we arrived helped to make the soil good for digging although it was
generally overcast and cool.
The
super 6 were Alex, Peter, Colin, Irene and self and Sarah a new member.
She has the right "ology" although
confesses it was 18 years ago. That is only yesterday as far as Bob is
concerned! Sarah has also had experience in excavating Bronze Age site(s)
in the past so we are very pleased she has joined us.
We
continued to take the trenches down and also removed some of the gravel
layer which seems to be over the central grey soil. I am not sure what it
has revealed so hopefully Aileen is back from conquering
After
3 1/2 years of finding everything else, Alex found her first good sized
worked flint and Peter has continued his weekly success with another. I
found a piece of pottery a long way down where the gravel meets the grey
soil. It is quite smooth and rounded on on
side so may be a piece of the rim of a pot.
Dig Report
Saturday/Sunday 2nd/
It
was glorious sunny weather and I think the Gods or Bob were shining on us.
With
Aileen back after her successful conquering of
Now
at this stage I must add that other great work had been carried out on the
site by Liz, Clive, Elie and Irene, continuing
to take down the trenches. Clive made 2 nice worked flint finds.
At
10.00 on the Sunday we resumed, initially doing the necessary paper work, and
then the total excavation of the pot pit. Apart from a hole in the
base it was in one piece but with some scary cracks and a bulge on the side
that did later fall out. After a lot of finger tip work in the confined
pit space we managed to uncover the whole pot and Clive managed to arrange for
Stuart, Chair of the Ely Archaeological group and photographer with
English Heritage, to attend and take some professional photos for us.
The
pot was wrapped in more cling film than Tesco's use
in their packaging, to hopefully support the pot whilst it was finally being
removed and transported. We then dug out one side if the pit to get
better access to it and after some redesigning of a hand shovel, Tony got gown
and close with Aileen to undertake the final excavation and lifting of the
pot. A huge sigh of relief when it came out with a good coronet of soil
to keep all the contents in place. Apparently after the cremation the
pots were filled with the ashes and then inverted in the pit. Sometimes
with Iron and Roman pots, they were damaged deliberately with a hole so they
would not be of use to anyone else.
The
collared urn is (hopefully) at
In
the meantime, here are some more pictures which hopefully will reward you for
some of the hard work that has been put in over the last 3 1/2 years. We
still have a lot more to do and still have to look for some associated burials
and maybe a whole Bob not in a pot!
Dig Report
We
started in the rain and gave up early because of it, but there was a
window, or 2, or 3 in-between that allowed us to get some work done. Was
Bob throwing a tantrum?!
Before
I continue can I apologise for omitting, in my report
of 2nd June, to welcome Denise Chappell to our group. It seems as though
Denise brought good luck with her. Initially she struggled to find us but
was not put off and her perseverance was rewarded as within a very short
time of her arrival, the urn was found. Thank you for this. It has
only taken us 3 1/2 years and is a welcomed boost to us all. What will we
find next time you join us?
Also,
for not thanking Tony for all his gardening work. The trouble is not
finding enough time to do all the excavation work and keep the area tidy and
looking professional, as we all are now! The central bulkheads were very
nicely trimmed and all the weeds surrounding the mound
were removed. Tony, can you come back in 2 weeks time as with all
this rain, they have grown again!
Despite
the weather, this week had a good turnout of 9. Nearly into double
figures - Aileen, Alex,Gill, Elie,
Sarah, Peter, Clive, Irene and me. We continued to take down the trenches
and made good progress. The bad news is that from the attached pictures
you will see the Urn pit was about 50cm deep and the bottom of it appears to be
where the original base level is. Most of the trenches are lower
than the top of the pit but we still probably have about 30cm, or 12 inches in
old money to go. No problem for a top team like us. The only
concern is we are rapidly approaching sea level. Not to worry, we have
our buckets and spades.
After
the dreaded but essential paperwork, I continued with excavating the other pit,
context number 806. I soon found a thin very dark if not black
layer. We are not sure what it is but initial thoughts are maybe cloth or
a wicker basket. It does not appear to be in a stable enough condition to
enable us remove it so will have to record, photograph and take
samples. More "lovely" paper work. I joined an
archaeological dig to become a pen pusher!!!!!!!!!
From
looking at the pits and the surrounding soils, Aileen is of the
opinion the urn is a secondary burial and Bob (who still lives on!)
should be in a pit dug beneath the base level of the mound. We all
thought we were digging to the base level. Now we could be heading for
The
rain also gave us a chance to view the photographs that Steve took for
us. Clive, will you please pass on our thanks for the great pictures and
also for not charging us for them. I understand he appreciated the
opportunity of being able to witness our find. I think all of us
who were there also enjoyed being part of it.
Our
task for next week and possibly a few more, is to excavate 2 more areas in the
corners between the EW & NS trenches. We need to leave bulkheads of
30cm and then take out 1m wide by about 1.5m long areas so we can see as soon
as possible if there are any more secondary burials near the 2 pits we have so
far discovered. We also need to continue to take down the trenches,
initially concentrating on the central area and then working outwards.
Dig Report
It
rained just before we arrived on site and had another go just after we left,
but otherwise it was good digging weather. Shame about the puddles that
did make it a bit interesting in parts of the trenches. I suppose we will
have to get used to it as we are rapidly, well perhaps that is a slight
exaggeration, approaching sea level. In the pit where the urn was, the
tide was definitely in!
A
super six day with Alex, Cecilia and Gill, fresh after her hols,
Elie, Irene and self. It was nice to have a
bevy of ladies but guys I do need some support at times! We are sorry to
hear Sarah's back is playing up, so could not be with us. Best
wishes for a speedy recovery.
We
started 2 further pits in the corners between the EW & NS trenches
and managed to excavate them down to about the level where we found
the soil changes for the urn and other pits. Unfortunately, they don't
indicate any more pits, at this stage. Gill did find another worked
flint.
Alex
arrived later as Dave needs new glasses. No, I am not saying anything, as
if I would! She continued to reduce the level in the NS trench without
getting inundated by the surrounding puddles, which was no mean
feat. Her efforts were only rewarded by finding some more gravel
deposits.
I
continued to excavate pit 806. The dark layer, which may be a wicker
basket may have a handle or a sausage shaped something in it. It doesn't
seem to go across the whole width from N to S. After re-measuring the pit
section and completing the context sheet, I started taking down the west side
of the pit. About 5cm above the dark layer, there is a very hollow
sounding area with a hard but distorted surface that may be square or
angular. As it was late or should I say in the Time Team zone, we
photographed it and covered it up until next time. Before we proceed
further, I think (hopefully) it will be advisable to have Aileen's
support. I am also not sure if the two pits overlapped each other or if
it was an oval shaped one. The central section is not gravely like
the surrounding area to the two pits.
Dig Report
It
was lovely sunny weather with a pleasant breeze. Ideal for digging so
Denise, Peter, Elie, Jane, Clive Irene and myself
set-to. A special nautical term to welcome Clive back after his sailing
holiday.
Irene
put the hoe that had been gathering cobwebs in my garage to good use and
cleared all the weeds, until next week! She then continued reducing the
level of the eastern part of the EW trench. Clive joined us and removed
the end part.
Elie continued reducing the western end of this trench
although we have now proved she doesn't have a level eye. I wondered why
the museum had some displays that slope! After Peter and Denise had
finished taking down the NS trench Elie gave them
some training in the use of the dumpy and the levels are at or slightly lower
than the base level just outside QA. It therefore appears that we have
got to base level in this trench. If so, I am sorry to say Peter, this
could be the end of THIS Forth Road Bridge. I am sure I can find another
if you ask. There is still the apparent context change, and Elie then taught Denise and Peter how to prepare Context
Sheets. Next time will be investigating it to see if it is a
pre-mound pit or, heaven forbid, it is a layer of different soil that is under
the gravel and therefore we will have to continue our journey to Australia!
Jane
had a look at the westerly test pit and found a context change that seemed to
continue from the NS trench by pit 806. Having prepared a context sheet,
photographed it, recorded it on the QA plan, she then found the soil change
petered out after a few inches! No Peter I am not using your name in
vain! Never mind, it was good practice and we will have to finish taking
out the extra half meter next time.
I
spent my time trying to remove the soil from above the black layer in pit 806,
whilst leaving the black layer behind. It was a bit of a job trying to
get the mattock in! Don't panic Aileen, just joking!!!! I think I
have achieved this but there seem to be a couple of other features that I would
like you to look at before I finish and then remove the black layer to then
create another context and see what else is in this second pit.
Dig Report Saturday 4th
August 2007
It
was a hot one but thank goodness there was a pleasant breeze. It is
amazing how quickly the site has dried out. A good turnout with Alex,
Irene, Cecelia, Aileen, Peter, Clive and "moi"
on duty.
Cecelia
and Alex continued in the test-pits and Irene and Aileen worked on the EW
trench. Aileen found a context change which will need recording next
time. Generally we now seem to have got to base level in all these and the NS
trench. We now need to record what we have excavated so this will mean
cleaning up the sections and then recording them on the permatrace
and context sheets. Once this is done, we will probably try to arrange
for the gravel site workers to remove a layer off this quadrant and maybe QD,
the unconquered one, down to the level where we found the urn and present pits
to see if we can find any more.
I
have got down to the black layer in the pit, photographed and recorded
it, so next week it will be removing this layer and then progressing
further down into the pit, "below the black layer". I am not
sure if this is mysterious or scary?!
We
have now returned to the 2nd quadrant, also known as the NW frontier or
QB. The purpose is to put in 2 new trenches. The first which has
been started will give us a complete EW section through the mound. The
second trench will be NS and we will then return to the very first quadrant
(QA) so we will then have a NS section. The two trenches in QB, we will
dig to context so after we finish the initial clean to identify soil colour changes, we will excavate the ditch areas
first, assuming the fill is over the mound, until we find the slump layer from
the mound into the ditch. Peter found a worked flint and there were a few
nearly ones that possibly would have got bagged in our early days.
Hopefully
the weather will enable us to continue making good progress so we WILL have
most if not ALL the work done by the end of the digging season so the report
can be written during the winter months.
Dig Report Saturday 11th
August 2007
Anyway,
it was hot, sunny and little wind and the soil was hard! Otherwise it was
fine and the crew of Peter, Denise, Cecelia, Alex, Irene and Self were joined
by new (village) boy Vic Williams.
Vic
was a great addition and together with Irene got most of the elevations of the
two trenches upright and clean so hopefully this week we can record the
sections and the various context changes.
Alex
also got the sides of the eastern test-pit upright and clean, again so they can
be recorded onto permatrace.
Cecelia
has now levelled the western test-pit. It
appears as though the context changes were natural or plough. The context
sheets need to be finished and this is now also ready to have the sections
recorded.
Peter
was in QB and did a great job cleaning the surface of the new trench so we
could identify the context changes and photograph them. We can clearly
see where the mound has slumped into the ditch and the ditch fill. This
week it will be removing the ditch fill.
Beside
keeping everyone organised carried on with pit
807. The black layer has been removed and the soil retained as another
sample. I have again sectioned the pit and removed the soil on the
eastern side to another black very loose layer.
Dig Report Saturday 18th
August 2007
We
were lucky finding the window in the rain to allow us to dig even although
it was cool and windy. The rain had made the
soil good for digging. A good turnout of 8 with Gill, Vanessa,
Denise, Cecelia, Elie, Vic, Peter and self getting
down but not too dirty as a lot of paperwork was also done. Now we are
all becoming pen pushers! Irene's mum is making good progress and
hopefully she will be able to join us again next week. It was great
to have Vanessa join us again after all the tremendous work she had done
over the first 3 years.
Gill
organised marking out a new North South trench in
quadrant B that follows through to the bulkhead in QA. Vanessa and
Vic helped her clean this and once the slumped area was identified, Gill then
removed the fill of what might have been the ditch but if so the mound was not
round!
Peter
started removing the fill from the ditch area in the EW trench of QB.
Nothing found but he enjoyed the softer fill soil rather than the hard and
compacted stuff in QC trenches. Going west was not such a bad
thing! Peter also wonder if there is a context change nearer to the
new NS trench. It looks a possibility but it is quite large at about 1 metre diameter.
Cecelia
completed the context sheets for the western test-pit in QC and then helped Elie to draw the east facing section of the NS trench in
QC. Only 3 more to do and the test pits!
Denise
finished excavating the change of context in the NS trench of QC.
Unfortunately it turned to the gravel base level after about 10cm.
Anyway, it was a good introduction to context sheets that were duly completed.
In
my spare time I removed some more soil covering the new black layer in pit
807. Next week it will be recording it on the pit's section and create a
new context sheet. After Aileen has had a chance to check it
we will be able to progress further.
Thank
you Aileen for arranging the experts to review the urn and it's contents.
We will watch this space with great interest as we gain a greater understanding
of what we have recovered that otherwise would have been lost under the gravel
extraction machinery.
Dig Report Saturday 1st
September 2007
I
know it didn't rain but that is it for the weather report! Numbers were
down as well but we did make some progress.
Alex
and Irene continued with the new NS trench in QA and Gill worked on the NS
trench in QB. One interesting flint was found together with the good old
mole plough holes. I drew the additional information on the permatrace for the section of pit 807 and completed (well I
think they are) some more context sheets.
We
then took a monolith sample from the east facing section of the pit.
Basically this is a 3 sided piece of metal, a bit like a gutter, that you hit
into the section to extract a soil sample running from top to bottom.
From this we hope to be able to work out when the various layers were formed
and how, e.g. placed there by man, natural or blown or washed in. This
additional information will hopefully enable us to gain a greater understanding
of how the pit was filled. We also plan to take a similar sample from one
of the sections to try to get a greater understanding of how the mound was
formed and why there seem to be so many context changes.
From
this I hope you can see that we are preparing ourselves for writing the report
this winter. It also means we need to get on and complete as much as
possible before the weather changes, not that it probably can get any worse
than this summer!
The
work, I think we need to do is
- Complete removing the soil in
the trenches. That is the NS one in QA and the NS & EW ones in
QB.
- Finish recording the sections
onto permatrace.
- The existing one for QA will
need to have the new information added after the NS trench is fully
extracted.
- At least 2 for QB, if not 4!
- 3 more sections for QC.
- Finish removing the contents
on pit 807 - nearly there!
- Remove the bulkheads in QC
between the 2 test-pits and the trenches
- Arrange for a JCB to take down
QC soil to the same level as the level at which we found the soil changes
for the 2 pits and possibly undertake similar work in the other 3
quadrants.
- Check the JCB removed soil for
finds.
- Excavate any more pits that
are revealed and find BOB.
I
am feeling tired at this stage so will stop looking for things to do! In
short there is still a lot to do and if you can make it over the next
weeks for the BIG FINAL PUSH then it will be great
to see you there.
Dig Report Saturday 8th September 2007
It
was good weather for digging, warm enough for short sleeves but not too hot to
slow you down. That is a good job for me as slower than slow must be
stopped!
It
was also a good turnout with a mighty 7 plus Aileen to check on our progress
and being happy, then excavated more of the ditch in the NS trench of
QB. The "pot lady" is coming this week or early next and
not satisfied with the big pot plus about 12 smaller finds, Aileen found a
piece and a bit, in the ditch. Super, all contributions gratefully
received.
Good
progress was made in the 2 NS trenches in QA & QB by Irene, myself, Elie, Denise and Sarah. Peter continues to make good progress
taking the ditch out of the EW trench in QB and as mentioned, Aileen excavated
more of the ditch in the NS ditch in QB. This now seems to be a lot
closer to the centre than we think, from memory, than the previous
recording showed. From the new work now being done in QA, we are
beginning to wonder if the ditch is wider than we originally thought which will
make the mound smaller. We could well have been confused by the
gravel that slumped off the mound mixed with other soil that made us
think the ditch was further out. We will have to check where the
gravel base really is. All good archaeological detective work!
The bad news is, we may have to make all the ditch excavations bigger.
That includes yours Peter. Now you know why I said we should call it the
Seven Road Bridge!
Jane
paired up with Elie and together have recorded the
west facing section of the NS trench in QC. This is where Terry can tell
you about his new toy! I have discovered an option on some software I
have had for 2 years that allows you to stitch pictures together. Where I
have taken a series of pictures of sections, I can now get the
computer to merge them into one complete view. The system is perfect, the
only flaw is the bunny who operates the camera! You need to make sure
each picture is taken at right angles to the section and at the same elevation
to ensure you don't get any distortion. Anyway, I thing they are pretty
good; what about you?
The
other thing I can report is the 807 pit is almost there. Despite putting
in overtime to 6.30 I ran out of everything and had to call it a day. The
bottom has quite a thick layer of black ash, some of which could possibly be
cremated bone. Aileen has taken the samples to have them viewed under a
microscope. I will let you know the results. The only thing I want
to know is why was Rachel given a present in the cremation pot (the
hand knife) and I haven't?!!!!!!!!
Unfortunately
Aileen agrees with my quick list of what we need to do, hopefully before the
end of this digging year so we can have as much data to enable the report to be
written over the winter months. Whilst we will try to carry on as long as
possible this year, there is possibly only 6 -8 more weeks we can rely
upon. So please don't miss the chance to get down and dirty before 2008
is with us, and help with the big push!
Dig Report Saturday 6th October 2007
In
some respects, a dig report is a waste of time as we had 14 eager beavers on
site so most already know the story. I fear it was
the thought of a big man in a JCB that was the attraction!
The
weather was kind and we were also lucky that the site had hired in a
nearly new JCB to scrape back some of the banks that had slipped into the
reservoir and it was there for our use. This meant Alan, the operator
could make quite precision scrapes of QC and then QD under the watchful eye of
Aileen. In about 2 hours more soil was removed than we can do in 2
years. Unfortunately or fortunately, depending on your viewpoint, no more
context changes were found to indicate any more possible pits. We
were able to identify the ditch following through from QA into the southern
edge of QD.
We
managed to work our way through about half of the scrapped soil and found 5
small flakes of worked flint. The star of the day was Vanessa who found 2
great worked flints, photos are attached. I am sure Tim will be very
interested in seeing them as they must nearly be as great as the hand knife
found in the urn.
Thank
you all for all your efforts on Saturday and remember there is still a lot more
to do in less than 24 hours time. I still need the macho diggers, the
eagle-eyed, the tidy ones to clear up after the JCB as well as those who
can/would like to help record the sections, plan drawings etc. I
hope we will break our record numbers again this week.
I trust I didn't hear "Dream on"!!!!!!!!!!!!!!
Dig Report Saturday 13th October 2007
Again the
weather was good to us even though there had been a lot of rain the previous
few days. This meant Elie had to bail-out the
water that had collected on the plastic sheeting in the ditch in the EW trench
of QB. I did do a Health and Safety check and yes she has got her 50 metre swimming badge! Our friendly toad was still on
duty but had to be temporally relocated. The difficulty with the
trenches is trying to differentiate between original top soil/gravel and what
has slumped back into the ditch. Elie has taken
1/3rd of the inner part back and we can now see more clearly what we think are
the various layers. It has proved that a lot more needs to be
removed!
I can say the
above as I had a session in the ditch of the NS trench, same quadrant. A
bit more to finally remove but nearly there. I have found what may
be some traces of a small layer of burnt material. On the other hand it
is probably be nothing. Will have another look next week.
Cecelia and
Irene checked and removed the remaining spoil from QD. Unfortunately the
gravel men had removed one pile that we had not had a chance to check, but such
is life! Gill did a mammoth job of cleaning the E facing section of this
quadrant and it is now ready for recording. We still have to do the S
facing section and clean the surface, but otherwise it looks quite neat
already.
Jane & I
finished the E facing section of QC and Jane has cleaned about a 2 metre wide area of the surface.
All in all, a
lot of tidying and work was done by the 6 of us.
Dig Report Saturday 20th October 2007
A
good day and a lot of hard work was done as well as the essential recording.
The
3 Mattockeers, a.k.a. Cecelia, Vanessa and Vic
did a great job tidying up the south facing section of QD and started to clear
the trenches in QC that got filled by the JCB when it did the
scrape. The section just needs the final clean and then recorded.
Sounds simple!
Alex
and Denise started recording the East facing section of QD and were surprised
how many context changes Aileen found for them to record!
Irene
& I were in the ditches in QB. Irene continued to take it back to the
gravel on the east side of the ditch in the EW trench and now "just"
has to follow the gravel down, making it deeper. The Ditch in the NS
trench is nearly fully excavated. After finding a silty/clay
layer over the gravel, this then tried to confuse us by having a lens of gravel
over it before reverting back to the silty/clay.
There is also an interesting cut through the gravel running in a NE - SW
direction. Should get the last layer out today and then this can be
recorded with the W facing section so we can link it with the one Alex &
Denise were recording to give us a complete NS section across the mound.
Dig Report Saturday 27th October 2007
Considering
the clocks went back last night, it was good weather for working.
It
was very much a day of tidying up and finishing and almost finishing the
ditches ready for recording.
Gill,
Vanessa, Vic & Clive did a great job removing all the spoil from QC.
Vanessa found a nice worked flint and Clive rediscovered a possible
pit. Where it had been refilled with soil it did look "interesting"
for a while but turned out to be the possible pit Denise had previously
explored. Just a final surface scrape next time and it can be recorded.
Irene
has found gravel on both sided of the ditch in QB - EW trench and hopes there
is just a bit to be removed from the bottom. I hasten to add that is, of
the ditch!
I
have decided the ditch in the NS trench of QB is finished. Being 900mm
deep, it is finished!!!!!!!!! That is, apart from recording it and the W
facing profile.
The
next few weeks will be very much the final recording of all we have achieved
over the last 4 years. I attach photo from September 2004 as a
reminder of what we have achieved, and that is without all of the finds we have
collected. For those who have not done the recording of the sections and
plans before, it is not that difficult and by pairing up with others who have,
I know we will get some good results. That does mean we need both those
who have had some experience and well as our "virgins"! Aileen
should also be there to help us identify the context changes.
I
feel we are progressing well although there is still quite a lot to do
including the final tidy up for the final pictures and the removal of the
central cross baulks. Hopefully with everyone's support and the weather
remaining kind, we will be able to achieve this over the next 5 weeks,
unless we have a "Time Team" drama with a last minute significant
find! I am sure we won't mind if it is another urn pit.
Dig Report Saturday 3rd
November 2007
I am not sure
if you are aware but this year we have so far managed to undertake 27 Saturday
excavations. We lost 2 in July due to bad weather and one Saturday
when Irene & I dared to have a day off, but I think 27 out of a possible 30
has been really good. Our average numbers must be about 6 or 7 which
again is very good. Weather permitting, and enthusiasm being maintained,
we should be able to push this up to 31 by the proposed end of this year's
digging, i.e. 4 more to go.
Again the
weather was great although the chill crept in when the sun went down and it
also got dark about 4.30.
Alex with
Vanessa on the tape, completed the drawing of the East facing section of
Quadrant D. This could only be undertaken after the datum line was checked
to be in the correct position. Vanessa had a quick refresher course on
how to use the dumpy, and after a short time, which felt like hours
for the poor person holding the measure, she became a "Dumpy
Expert". Vanessa insists her figure is not Dumpy, it is just
the shape of the overalls and as for being an Expert she feels she is not a
"former" (Ex) and definitely "not a drip under pressure"
(spurt)!!!!!!!!!!. Alex and Vanessa are now in the process of deciding if
any of the contexts are the same and then allocating Context numbers. We
then will have the fun of trying to decide if they are similar to other section
contexts in the first 3 quadrants.
Jane & I
cleaned and identified the context changes on the south facing section of the
same quadrant. We have started recording it in the permatrace
but "bad light stopped play"!
Irene is well
on the way of finishing the ditch in the EW trench of quadrant B. She has
found the gravel on both sides and hopes there is not much more to take out of
the bottom. It is then deciding if she is back to the gravel on the east
side or if there is some more material that needs to be removed
before she can call it a day.
Try as Aileen
could, she had to admit that the ditch in the NS trench of QB that I decided I
had finished excavating last week, is in fact completely excavated.
Bearing in mind it is about 1 metre deep, I don't
think it had anything to do with me standing at the top of the hole with a
mattock!!!!!!
Work still to
do -
- Allocate and record the context
numbers for the East facing section of QD
- Complete the recording of the
South facing section of QD
- Clean and record the plan of QD
including the small amount of ditch on the southern end before it is
truncated by the gravel workings.
- Excavate a small 1/2 x 1 metre area at the end of the EW trench by the
central baulk to establish and record where the gravel level is.
- Clean and record the North and
East facing sections of QB, including the ditch areas. This will
then give us complete EW & NS sections through the whole mound.
- Record the East facing section
of the ditch in the NS trench of QB as it is significantly different to
the other side.
- Amend the West facing section
of QA to record the additional excavations.
- Generally tidy up so we can
take the final pictures. If anyone has a petrol powered strimmer, it should make life a lot easier.
- Anything else we discover still
needs to be done after Aileen's next and last visit of the year, on the
17th November.
Dig Report
What
can I say. It started wet, it continued to be very windy which made it
cold. A generally miserable day, but the company was great.
Irene
decided the best place was
Vic
has taken down the area at the far easterly end of the EW ditch in Quadrant B
and has found the gravel layer. Clive has cleaned the west and north
sections of QB so other than waiting for Irene (I will be in trouble!) these 2
sections are ready for recording.
Denise
and I have set up the datum line and are a good halfway through recording the
east facing section of the ditch in the NS trench of QB. Irene was right,
being in a 3 foot deep ditch does keep you out of the wind. It is just
when you stand up that the wind knocks your head off. I Remembrance
Sunday the next day, the saying "keeping your head down" seemed very
poignant.
Alex
and Jane braved the elements in QD and finished recording the second
section. Not and easy job when the wind wanted to take everything away; permatrace and voices giving measurements and body
heat from the wind chill factor were amongst the problems. Context
numbers have been allocated and sheets started. Some help from Aileen on
linking common context will be greatly appreciated.
I
am sorry there are no pictures this week as trying to battle the wind was
enough and the light faded again too quickly. Whose idea was it to put
the clocks back?! I do attach a nice one from a couple of weeks ago which
I missed with the circulation.
Dig Report
Can we do it? Yes we can!!!!!!!!!!!
At
least it was dry and not windy but it is mid November and after 4 hours on
site, it felt like it. Definitely thermals is the order of the day!
Irene
continued with excavating the ditch in the EW trench of QB. I think she
is trying for a new record as to how deep she can make it! We have to
have great respect for our brothers 4000 years ago who dug these ditches to
about 3 feet or 900mm deep with their ancient implements. Bob must have
been a great person to generate this dedication, not only 4000 years ago but
now as well. It will be finished this week, but where have we heard that
before?!
Clive
and Vanessa cleared the southern part of QD so that is now ready to record onto
permatrace, showing the ditch area that comes through
from QA.
Denise
and I finished recording the west facing section of the ditch in the NS trench
of QB and allocated about 15 context numbers.
Aileen
did a great job, identifying the soil types and Munsel
colours of all the context of the 2 sections in
QD and also the above ditch section. These have been recorded on the
permatrace so we can sit down in the warm and
transfer them onto the context sheets.
So
basically we have the 2 sections in QB to draw and the plan of QD, plus a bit
more ditch. With your help we can do it so we will have enough information
to enable us to "tell the story" during the winter months.
Those
who are still totally dedicated can decide is if we want to return next year to
totally excavate all the ditch. It would be nice though not totally
essential. Don't ask Irene what her view is tomorrow as I think having
spent XXX weeks in the EW ditch, and this was after the excellent work done by
Peter and Elie, the answer may be very short and mine
may be ever shorter!!!!!!!!!!!!!!!!!
Dig Report
An
interesting day! It was cold and windy but we did find that small window
in the rain so stayed dry. To show how cold it was, there was still ice
on top of the plastic sheeting of QB so I nearly lost Irene straight into her
ditch, just by trying to remove the covering. I am sure there is a
section in Health and Safety that covers this but anyway, with some tip-toe
movements and a good tug, we got the covers off, moving the offending water and
ice straight into the ditch so Irene could spend the next 15 minutes bailing
out. A good job we were too busy surviving so the cameras did not come
out so we won't be on You've been Framed!
Clive, Denise
and myself ran away and left Irene to it and drew the plan of QD. Quite a
simple job really but the mud was nice and slippery as well and the wind
grabbed voices and threw the shouted measurements away. If we have
ended up with a plan that bares no resemblance to the site, you will know
why. We have also drawn another plan of QB, recording the 2 trenches and
now need to add the locations of the Sections we have and will be drawing.
Irene was
happy she had got to the bottom of the ditch in the EW trench of QB, especially
as it is now about 850mm deep. Down there she had no complaints about the
wind! She then made the mistake of looking at it again and now wonders if
there is some slumped gravely soil on the west side that still needs to be
removed. A glutton for punishment, which you all knew as she has been
married to me for over 35 years!
Now in good
old Time Team manor, we have come up with a conundrum that hopefully can
be resolved by studying the information we have collated, during the winter
months, whilst preparing the report. Now remember the conditions, so
this is definitely NOT scientific, but Clive & I took some quick
measurements, initially to see where the truncated ditch could be. In
doing so, we believe we have found that the 2 pits we excavated in quadrant C
are not equal distanced from the identified ditches. As I have said
this is probably total rubbish, or could it be the mound was not
round or the pits were not in the centre or ..... BOB is hiding closer to or
under the baulk between QC & QD?!